Project Development Updates

Current Updates

  • November 11: During the November Board Meeting, PBK presented the two proposed projects to our Board of Trustees, including updated renderings that reflect recent design discussions. Both projects were approved by the Board (see renderings below).

  • December 2: Our district team met with representatives from PBK, LEAF, DIG, Kubala, and Drymalla Construction to review the 50% construction documents. This meeting marked the first opportunity to engage with the entire PBK design team assigned to our district. Discussions focused on the technical aspects of the projects, including HVAC systems, technology infrastructure, electrical outlets, and site-specific considerations.

  • January 6: The district met with PBK to review the 75% construction documents. During this meeting, topics included design changes, equipment, site utilities and existing conditions. Drymalla provided insight on construction feasibility and options.

Upcoming...

  • February 10: The district will meet with PBK’s design team & Drymalla Construction to review the 95% construction documents. This will mark the final meeting for the drawing phase before bidding around mid-march.

PROJECT updates

Project Development Updates

June 23, 2025 – Site Demolition Complete

The second OAC meeting took place, and the team reported that demolition is now complete at both sites. Site preparation is underway, with dirt work in progress to get ready for building pad installation at both campuses in the coming weeks.

June 9, 2025 – First OAC Meeting

The first OAC (Owner, Architect, and Contractor) meeting took place. The construction schedule was reviewed, and job sites for both projects are now fenced and secured; Demolition is set to begin at both sites. OAC meetings will be held every two weeks to discuss construction progress.

May 28, 2025 – Pre-Construction Kickoff

A Pre-Construction Kickoff Meeting was held with PBK, Columbus ISD, and Drymalla Construction. The team introduced key members of the construction crew, walked through the projected construction schedule, and discussed startup logistics.

May 12, 2025 – Board Approval Given

PBK and Drymalla presented the proposed Guaranteed Maximum Price (GMP) to the Columbus ISD Board of Trustees. The Board approved the GMP during this meeting.

May 1, 2025 – Project Review and Planning

PBK Architects, Drymalla Construction, and Columbus ISD convened to review subcontractors, potential project alternates, and the proposed budget. Construction contingency planning was also discussed to ensure flexibility moving forward.

April 9, 2025 – Bid Opening

Columbus ISD and PBK Architects joined Drymalla Construction at their office for bid opening day. Drymalla selected subcontractors and developed a preliminary estimate for overall construction costs.

March 10, 2025 – Construction Drawings Issued

Final construction drawings were officially issued to Drymalla Construction, kicking off a month-long competitive bidding process.​